Powered land is where the UK data centre market will be won

Data centres By Colin Dowdall, Associate Director, Critical Systems – 27 October 2026

Generated by AI

Authors

Colin looking to camera in a pale open collar shirt and suit jacket in front of a green plant wall

Colin Dowdall

View bio
Andrew Livesey looking towards the camera wearing a light blue shirt

Andrew Livesey

View bio
A person wearing a burgundy sweater over a checked shirt stands with folded arms in front of a textured green moss wall.

Kevin McGee

View bio

The UK is not lacking in interest regarding data centre development; what it lacks is a sufficient number of locations where land availability, power supply, planning approval, and regional ambition all proceed at the same pace. Currently, powered land serves as one of the best indicators of whether data centre projects can progress from opportunity to actual delivery.  

A data centre site is only as strong as its route to power. That may sound obvious, but it is already shaping important investment decisions in the UK. Earlier this year, OpenAI paused plans for its UK data centre project, with media reports citing concerns around energy costs and regulation. The lesson is clear: land, capital, and customer interest are not enough on their own. If the power strategy is uncertain, the project can quickly move from a strong opportunity to a difficult investment case.

This is where the conversation around data centres needs to change. For years, site selection has focused on location, connectivity, land ownership, and planning. These still matter, but they no longer tell the whole story. In many parts of the UK, the first question is now much more direct: can the site be energised, when can it be energised, and what has to happen before that becomes real?  

Without that clarity, opportunity remains just that. It does not become realised.  

Power has moved to the front of the programme

Power is an issue to solve from the start. It is a commercial issue from day one. For developers, the risk is simple: a site may look promising, but if the grid connection is unclear or dependent on long reinforcement timelines, the project carries too much uncertainty. That affects land value, customer commitments, investment decisions and programme confidence.  

It also affects whether the UK can hold on to growth that is already looking for a home. Operators want certainty. Investors want a credible route to delivery. Regions want the jobs, business rates, infrastructure, and wider economic activity that investment can bring. Yet too often the process between a good idea and an investable project is still too difficult to navigate.  

The issue is how much power is available. It is also how connection decisions are made, how readiness is measured, and how quickly viable projects can move through the system. NESO’s connections reform is intended to shift the process towards projects that are ready to progress, while Ofgem is consulting on data-centre-specific queue management milestones and commitment fees to reduce the number of speculative schemes holding scarce capacity. These reforms could help credible projects move faster, but they are not a complete solution. They may also increase early stage costs and place more pressure on developers to prove financial strength and deliverability before a project has full certainty. If the process becomes clearer but more expensive, some operators may still look to markets where the route to power feels simpler.  

Powered land needs more than a grid connection

A power land strategy involves more than just securing a site close to a substation; it is necessary to consider the site and the surrounding infrastructure as a whole. While grid capacity is important, so are the connection timelines, the need for reinforcement, planning risk, the availability of fibre, water, heat reuse, land control, and the broader development context.  

But that will not happen by accident. If each project is treated only within its own red line, it misses the bigger opportunity. A data centre can then be seen only as a large power user, rather than as part of a wider digital and energy ecosystem. In the right location, and with the right planning, data centres can help strengthen the case for infrastructure that supports more than one project.  

That could include new power infrastructure, heat networks, fibre investment, employment land, nearby technology businesses and future housing growth. The point is not that every data centre delivers all of these outcomes. The point is that they are only possible when the planning starts early enough.  

Regions need a clearer way to prioritise

More projects will always seek power than the system can immediately support. That makes prioritisation unavoidable. The problem is that the criteria are often unclear. Developers need to understand what makes one project more ready, more valuable, or more strategic than another - and public bodies need to understand what they are trying to unlock. Network operators need confidence that projects requesting capacity are credible and deliverable.  

Money alone is not enough of a test. A stronger framework would consider readiness, customer demand, land position, deliverability, social value, economic impact, and the wider infrastructure benefits a project can help create. It would also recognise that the best project is not always the one that shouted first or paid first. It may be the one that can unlock the most value for the region.  

This is where regional leadership matters. National Grid reform is essential, but many of the practical choices sit closer to the ground. Local authorities, combined authorities, network operators, landowners, energy developers, and data centre specialists need to be in the same conversation earlier. They need to understand the projects, the constraints and the trade-offs before timelines become critical.  

Without that coordination, projects can get stuck between organisations that all recognise the problem but lack a shared mechanism to solve it.  

The narrative around data centres needs to mature

Data centres are often described in terms of their constraints. They need power. They need land. They need water. They create planning pressure. They increasingly face public questions about resource use.  

Those concerns should not be dismissed. They need to be addressed through design, planning and transparent engagement. But they are not the whole story.  

Data centres are part of the infrastructure that modern economies now rely on. They support research, public services, financial systems, cloud platforms, AI development and the everyday digital tools used by businesses and communities. They can also attract wider investment when they are planned as part of a regional technology ecosystem, rather than treated as standalone buildings with servers inside.  

This is why the public and political narrative around data centres needs to move beyond whether individual schemes are acceptable. The UK, seeking digital investment, would benefit from a clearer policy framework for identifying ‘data centre-ready' locations. Germany offers a useful comparison. We explored this in a recent blog in relation to proposed changes to the German Energy Efficiency Act, the most effective regulation is not about lowering standards’ it is about giving operators clear, proportionate and deliverable rules around efficiency, waste heat reuse, reporting and long-term investment.  A similar principle could apply in the UK.  

From land search to delivery strategy

The UK data centre market is not short of ambition. The challenge is turning ambition into deliverable projects.  

That requires a different approach to site selection. Land, power and planning can no longer be assessed in separate workstreams. They need to be considered together from the start, alongside commercial requirements, customer timelines and regional infrastructure priorities.  

For developers this involves asking more difficult questions at an earlier stage - such as whether the power supply is genuine, if the method of achieving connection is believable, whether there are private wire options available behind the meter, whether there is an opportunity to reuse heat, whether the local stakeholders are in agreement, and whether the project aligns with a wider regional strategy or instead is based on a narrow, site specific argument.  

The situation is just as significant for regions. Which projects are truly ready? Which have the potential to generate greater value? And which ones require political and infrastructure support at this moment rather than afterwards, when the opportunity has already moved somewhere else?  

Powered land is where those questions meet. The winners in the next phase of the UK data centre market will not be those who find land. They will be those who can connect land, power, planning, and regional purpose into a credible delivery route.  

Whether you are a developer, investor or government organisation looking to answer the questions above, reach out to a member of our Energy or Data Centre team. 