Weston Road

New distribution warehouse covering 335,000ft2 (31,151m2) in Crewe’s commercial district.

CGI view of front facade and car park

行业领域

项目地点

Crewe, United Kingdom

客户

Trebor Developments

建筑设计

UMC

With a building height of 18 metres, and yards stretching 56 metres, this self-contained site has Grade A offices, loading doors and a private car park. Designed with sustainability in mind, the scheme includes with roof lights, roof mounted solar panels and EV charging points.

Our team secured 1MVA of electrical capacity to the site which previously had a limited supply agreement with no spare capacity available in the local network. This achievement was a result of close negotiations and extensive communication with the local Distribution Network Provider (DNO) to reach an optimal solution.

Eddie Allen, project manager, commented “The Cundall team worked hard to achieve the desired client brief with regards to power provision to the site. This combined with the efforts from Cundall’s sustainability team has provided an asset which gives tenants significant flexibility when it comes to electricity demand in an area which is very much limited on available supply capacity.”

Key fact

A total of 1,316m2 of PV panels have been installed on the scheme to provide a total of 293kWpk. It is anticipated that this will generate circa 272,000kWh/annum.

1/2

Key fact

A new hydrant ring with associated pump house, complete with resilient pumping arrangements, has been provided to the site. Future provision for a sprinkler system complete with sprinkler tanks and pump house has also been provided.

2/2

Eddie Allen standing in front of sunny green area

Eddie Allen

Associate Director, Electrical Engineering

查看个人简介

A great example of the Cundall team’s collaboration to meet the client’s brief with regards to tenant requirements and sustainability aspirations within the industrial sector.

相关文章